Sewage Treatment Plant Upgrade

Taylor, British Columbia

completeWastewaterISF
Federal contribution
$183,333
Federal share33%

of $550.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Taylor
Construction start
Aug 1, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2009