Back to projects

Communal Septic Tank

Pacquet, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$43,550
Federal share33%

of $130.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Pacquet
Construction start
Mar 4, 2011(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start19 months lateforecast Aug 1, 2009
  • Construction end21 months lateforecast Sep 20, 2009

Also in Pacquet