Paving By-roads

Pacquet, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$54,950
Federal share33%

of $164.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
2024
Built

Approved 11 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Pacquet
Construction start
Jun 1, 2024(actual)
Construction end
Jul 7, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2024
  • Construction end5 weeks lateforecast May 31, 2024

Also in Pacquet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67358 in the federal list. How to read these figures.