Sanitary Sewer Extension Town of Pacquet
Pacquet, Newfoundland and Labrador
Federal contribution
$162,218
Federal share33%
of $486.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Pacquet
- Construction start
- May 22, 2023(actual)
- Construction end
- Jul 14, 2023(actual)
Against the original forecast
- Construction end4 months earlyforecast Nov 15, 2023
Also in Pacquet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53881 in the federal list. How to read these figures.