Back to projects

Combined Sewer Elimination & Water Main Renewal

St. Stephen, New Brunswick

completeWastewaterCC
Federal contribution
$1.2M
$1,196,966
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 27, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of St. Stephen
Construction start
Jul 15, 2009(actual)
Construction end
Jul 14, 2012(actual)

Also in St. Stephen

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22827 in the federal list. How to read these figures.