Milltown Boulevard (King Street to Hawthorne Street) - Watermain and Sanitary Sewer Renewal
Federal contribution
$1.3M
$1,300,325
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of St. Stephen
- Construction start
- Jun 21, 2017(actual)
- Construction end
- May 9, 2019(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 15, 2017
- Construction end6 months earlyforecast Oct 31, 2019