Back to projects

Milltown Boulevard (King Street to Hawthorne Street) - Watermain and Sanitary Sewer Renewal

St. Stephen, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$1.3M
$1,300,325
Federal share50%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of St. Stephen
Construction start
Jun 21, 2017(actual)
Construction end
May 9, 2019(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 15, 2017
  • Construction end6 months earlyforecast Oct 31, 2019

Also in St. Stephen

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48220 in the federal list. How to read these figures.