Combined Sewer Separation and Utility Renewal - Union Street
Federal contribution
$1.1M
$1,068,000
Federal share61%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of St. Stephen
- Construction start
- Jul 15, 2021(actual)
- Construction end
- Jun 25, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast May 3, 2021
Also in St. Stephen
- Garcelon Civic Centre$6.2M
- Milltown Boulevard (King Street to Hawthorne Street) - Watermain and Sanitary Sewer Renewal$1.3M
- Elm Park, Pinewood, and Maple - Sewer Separation and Infrastructure Renewal$1.3M
- Combined Sewer Elimination & Water Main Renewal$1.2M
- Prince William Street Infrastructure Renewal$929.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57018 in the federal list. How to read these figures.