Water and Sewer Extension - Valley Drive
Hawke's Bay, Newfoundland and Labrador
Federal contribution
$60,531
Federal share33%
of $181.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.9 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Hawke's Bay
- Construction start
- Jun 10, 2010(actual)
- Construction end
- Aug 9, 2011(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 1, 2009
- Construction end20 months lateforecast Nov 30, 2009
Also in Hawke's Bay