Upgrade Lift Station

Hawke's Bay, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$68,198
Federal share36%

of $188.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Hawke’s Bay
Construction start
Aug 30, 2017(actual)
Construction end
Sep 21, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 6, 2017
  • Construction end5 weeks lateforecast Aug 15, 2017