Pump House Upgrades
Hawke's Bay, Newfoundland and Labrador
Federal contribution
$85,780
Federal share30%
of $290.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
201920202021
Built
Approved 2.5 years before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Hawkes Bay
- Construction start
- Jun 22, 2020(actual)
- Construction end
- Jun 21, 2021(actual)
Against the original forecast
- Construction start2 months earlyforecast Aug 31, 2020
- Construction end5 months earlyforecast Nov 30, 2021
Also in Hawke's Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52911 in the federal list. How to read these figures.