Trunk Sewer - East End
Federal contribution
$1.4M
$1,400,000
Federal share28%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 24, 2009
20102011
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Riverview
- Construction start
- Apr 12, 2010(actual)
- Construction end
- Jan 24, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast May 1, 2010
- Construction end3 weeks lateforecast Dec 31, 2010
Also in Riverview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22885 in the federal list. How to read these figures.