Water and Sewer Upgrades on Various Streets

Riverview, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$1.2M
$1,214,926
Federal share50%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Riverview
Construction start
Jul 31, 2017(actual)
Construction end
Sep 24, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 4, 2017
  • Construction end8 weeks lateforecast Jul 31, 2018

Also in Riverview