Water and Sewer Upgrades on Various Streets
Federal contribution
$1.2M
$1,214,926
Federal share50%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Riverview
- Construction start
- Jul 31, 2017(actual)
- Construction end
- Sep 24, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 4, 2017
- Construction end8 weeks lateforecast Jul 31, 2018
Also in Riverview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48243 in the federal list. How to read these figures.