completeWastewaterNRP
Federal contribution
$22.6M
$22,601,944
Federal share25%

of $90.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 12, 2016
2017201920212023
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Dec 12, 2016(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start4 months earlyforecast Apr 15, 2017

Also in Riverview