Expansion of Existing Secondary Treatment Process

Fredericton, New Brunswick

completeWastewaterCC
Federal contribution
$1.7M
$1,666,666
Federal share33%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2009
20102011201220132014
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Fredericton
Construction start
Jan 14, 2011(actual)
Construction end
Nov 15, 2013(actual)

Against the original forecast

  • Construction start15 months lateforecast Oct 1, 2009
  • Construction end2 months lateforecast Aug 31, 2013

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22921 in the federal list. How to read these figures.