Upgrade of water distribution system

Richibucto, New Brunswick

completeDrinking WaterCC
Federal contribution
$314,963
Federal share33%

of $944.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 30, 2009
20092010201120122013
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Richibucto
Construction start
Nov 25, 2009(actual)
Construction end
Jan 29, 2013(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2009
  • Construction end6 months earlyforecast Jul 31, 2013

Also in Richibucto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22941 in the federal list. How to read these figures.