Richibucto Water Treatment Plant Upgrade

Richibucto, New Brunswick

underwayDrinking WaterRNIS
Federal contribution
$2.1M
$2,082,000
Federal share60%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2024
today
2021202320252027
BuiltForecast

Approved 4.1 years before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Richibucto
Construction start
Aug 1, 2023(actual)
Construction end
Mar 31, 2027(forecast)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2023

Also in Richibucto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57017 in the federal list. How to read these figures.