Kent North Center - sport and recreation facility
Federal contribution
$3.3M
$3,300,000
Federal share33%
of $9.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2017
2018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Richibucto
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Nov 22, 2018(actual)
Against the original forecast
- Construction start5 months earlyforecast Nov 20, 2017
- Construction end4 months earlyforecast Mar 31, 2019
Also in Richibucto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49908 in the federal list. How to read these figures.