Wastewater Treatment Plant Upgrading

Saint Andrews, New Brunswick

completeWastewaterCC
Federal contribution
$976,324
Federal share33%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2009
20102011
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of St. Andrews
Construction start
Jul 22, 2010(actual)
Construction end
Mar 30, 2011(actual)

Against the original forecast

  • Construction end3 months earlyforecast Jun 30, 2011

Also in Saint Andrews

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22946 in the federal list. How to read these figures.