Back to projects

Saint Andrews - Market Wharf Rehabilitation - Phase 2

Saint Andrews, New Brunswick

approvedMarineGIS
Federal contribution
$2.3M
$2,256,409
Federal share40%

of $5.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 28, 2024
today
2024202620282030
BuiltForecast

Approved 13 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Saint Andrews
Construction start
Apr 1, 2026(forecast)
Construction end
Dec 31, 2029(forecast)

Also in Saint Andrews

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67902 in the federal list. How to read these figures.