Van Horne Trail Upgrades
Federal contribution
$1.2M
$1,200,000
Federal share81%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022202320242025
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Saint Andrews
- Construction start
- Sep 6, 2022(actual)
- Construction end
- Nov 30, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 4, 2022
- Construction end3 months lateforecast Sep 1, 2024
Also in Saint Andrews
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58448 in the federal list. How to read these figures.