Van Horne Trail Upgrades

Saint Andrews, New Brunswick

completeActive TransportationCVRIS
Federal contribution
$1.2M
$1,200,000
Federal share81%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2022202320242025
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Saint Andrews
Construction start
Sep 6, 2022(actual)
Construction end
Nov 30, 2024(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 4, 2022
  • Construction end3 months lateforecast Sep 1, 2024

Also in Saint Andrews

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58448 in the federal list. How to read these figures.