Reconstruction of Pumping Station #5
Federal contribution
$458,546
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2009
20102011
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Fredericton
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Apr 4, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Sep 1, 2009
- Construction end7 months lateforecast Aug 31, 2010
Also in Fredericton
- University of New Brunswick - Justice Building Renewal$24.9M
- Awitgati Longhouse & Cultural Centre$18.6M
- New Brunswick Broadband$16.5M
- Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal$12.6M
- Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton$11.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22980 in the federal list. How to read these figures.