Upgrade of Doaktown Wastewater Treatment Facility
Federal contribution
$934,088
Federal share33%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 14, 2009
20102011
Built
Approved 3 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Doaktown
- Construction start
- Aug 2, 2010(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2010
- Construction end2 months earlyforecast Aug 31, 2011
Also in Doaktown