Doaktown - New Well, Water Treatment Plant and Reservoir - Phase 1

Doaktown, New Brunswick

completeDrinking WaterRNIS
Federal contribution
$1.3M
$1,274,650
Federal share60%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2024
2021202220232024
Built

Approved 4.1 years before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Doaktown
Construction start
Aug 21, 2023(actual)
Construction end
Jul 30, 2024(actual)

Against the original forecast

  • Construction start23 months lateforecast Oct 2, 2021
  • Construction end8 months earlyforecast Mar 31, 2025