Doaktown - New Well, Water Treatment Plant and Reservoir - Phase 1
Federal contribution
$1.3M
$1,274,650
Federal share60%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2024
2021202220232024
Built
Approved 4.1 years before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Doaktown
- Construction start
- Aug 21, 2023(actual)
- Construction end
- Jul 30, 2024(actual)
Against the original forecast
- Construction start23 months lateforecast Oct 2, 2021
- Construction end8 months earlyforecast Mar 31, 2025