Doaktown - New Well, WTP and Reservoir – Phase 2

Doaktown, New Brunswick

underwayDrinking WaterRNIS
Federal contribution
$1.7M
$1,673,786
Federal share60%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2024
today
202520262027
BuiltForecast

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Doaktown
Construction start
Nov 1, 2025(actual)
Construction end
Dec 31, 2026(forecast)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2025

Also in Doaktown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67814 in the federal list. How to read these figures.