Enlargment of existing lagoon

Caraquet, New Brunswick

completeWastewaterCC
Federal contribution
$1.0M
$1,029,304
Federal share33%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2009
200920102011201220132014
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Caraquet
Construction start
Aug 16, 2010(actual)
Construction end
Nov 30, 2013(actual)

Against the original forecast

  • Construction start16 months lateforecast May 1, 2009
  • Construction end3 months earlyforecast Mar 15, 2014

Also in Caraquet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23004 in the federal list. How to read these figures.