Back to projects

Replacement of Watermain - Du Portage Street and St-Pierre Boulevard West

Caraquet, New Brunswick

completeWastewaterCWWF
Federal contribution
$1.6M
$1,557,055
Federal share50%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Caraquet
Construction start
Aug 28, 2017(actual)
Construction end
Aug 24, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2017
  • Construction end8 weeks lateforecast Jun 30, 2018

Also in Caraquet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48209 in the federal list. How to read these figures.