Replacement of Watermain - Du Portage Street and St-Pierre Boulevard West
Federal contribution
$1.6M
$1,557,055
Federal share50%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Caraquet
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Aug 24, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end8 weeks lateforecast Jun 30, 2018
Also in Caraquet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48209 in the federal list. How to read these figures.