Back to projects

Rehabilitation of Sanitary Sewer Pipe - St-Pierre Boulevard West

Caraquet, New Brunswick

completeWastewaterCWWF
Federal contribution
$467,883
Federal share50%

of $938.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Caraquet
Construction start
Oct 3, 2017(actual)
Construction end
Nov 9, 2019(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 21, 2017
  • Construction end3 months earlyforecast Jan 31, 2020

Also in Caraquet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48212 in the federal list. How to read these figures.