Upgrade of the Dryden Sewage Treatment Plant
Federal contribution
$10.0M
$9,966,666
Federal share33%
of $29.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Dryden
- Construction start
- Jul 26, 2010(actual)
- Construction end
- Apr 16, 2015(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Sep 1, 2010
- Construction end11 months earlyforecast Mar 31, 2016
Also in Dryden
- Dryden Recreation Centre Expansion and Mechanical/Envelope Retrofit$2.0M
- Raw Water Intake Pipe Twinning$632.3K
- Water Meter Implementation$496.6K
- Expansion and Upgrades to Dryden Go-Getter Senior Activity Centre$428.5K
- Multiple Structural Relining of Watermains under Canadian Pacific Railway Tracks/Yard at 5 locations$200.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23012 in the federal list. How to read these figures.