Upgrade of the Dryden Sewage Treatment Plant

Dryden, Ontario

completeWastewaterCC
Federal contribution
$10.0M
$9,966,666
Federal share33%

of $29.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Dryden
Construction start
Jul 26, 2010(actual)
Construction end
Apr 16, 2015(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Sep 1, 2010
  • Construction end11 months earlyforecast Mar 31, 2016

Also in Dryden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23012 in the federal list. How to read these figures.