Water Meter Implementation
Federal contribution
$496,572
Federal share28%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Dryden
- Construction start
- Nov 22, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 1, 2010
Also in Dryden
- Upgrade of the Dryden Sewage Treatment Plant$10.0M
- Dryden Recreation Centre Expansion and Mechanical/Envelope Retrofit$2.0M
- Raw Water Intake Pipe Twinning$632.3K
- Expansion and Upgrades to Dryden Go-Getter Senior Activity Centre$428.5K
- Multiple Structural Relining of Watermains under Canadian Pacific Railway Tracks/Yard at 5 locations$200.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32266 in the federal list. How to read these figures.