Schedule
Announced and approvedMar 19, 2021
20222023
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Dryden Go-Getters
- Construction start
- Jul 18, 2022(actual)
- Construction end
- May 25, 2023(actual)