Back to projects

Water System Improvements

Alma, New Brunswick

completeDrinking WaterCC
Federal contribution
$95,460
Federal share33%

of $286.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2009
20092010201120122013
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Alma
Construction start
Oct 19, 2009(actual)
Construction end
Mar 15, 2013(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 30, 2009
  • Construction end5 months earlyforecast Jul 31, 2013

Also in Alma