Water System Improvements
Federal contribution
$95,460
Federal share33%
of $286.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2009
20092010201120122013
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Alma
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Mar 15, 2013(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 30, 2009
- Construction end5 months earlyforecast Jul 31, 2013
Also in Alma
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23044 in the federal list. How to read these figures.