Village of Alma - New Municipal Wells and Related Infrastructure
Federal contribution
$419,743
Federal share60%
of $696.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
202020212022202320242025
Built
Approved 2 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Alma
- Construction start
- Sep 5, 2019(actual)
- Construction end
- Nov 30, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 15, 2019
- Construction end8 months lateforecast Mar 31, 2024
Also in Alma