Upgrades to the Wastewater Treatment Plant

Alma, New Brunswick

completeWastewaterSCF
Federal contribution
$116,530
Federal share33%

of $349.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2015
20162017
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Alma
Construction start
Aug 16, 2016(actual)
Construction end
Aug 28, 2017(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Sep 28, 2016
  • Construction end8 weeks lateforecast Jun 30, 2017