Upgrade to water distribution and fire protection systems
Federal contribution
$1.3M
$1,250,924
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2009
2010
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Grand-Sault
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2009
- Construction end12 months lateforecast Oct 31, 2009
Also in Grand Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23052 in the federal list. How to read these figures.