Back to projects

Upgrade to water distribution and fire protection systems

Grand Falls, New Brunswick

completeDrinking WaterCC
Federal contribution
$1.3M
$1,250,924
Federal share33%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2009
2010
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Grand-Sault
Construction start
Aug 10, 2009(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2009
  • Construction end12 months lateforecast Oct 31, 2009

Also in Grand Falls