Sports Field Upgrades
Federal contribution
$433,200
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 22, 2019
2019
Built
Approved 12 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Grand Falls Regional Municipality
- Construction start
- Oct 2, 2018(actual)
- Construction end
- Jun 20, 2019(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 13, 2018
- Construction end7 months lateforecast Nov 5, 2018
Also in Grand Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52644 in the federal list. How to read these figures.