Schedule
Announced and approvedMay 19, 2015
201520172019202120232025
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Grand Falls Regional Municipality
- Construction start
- May 26, 2017(actual)
- Construction end
- Nov 13, 2024(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 1, 2017
- Construction end4 weeks lateforecast Oct 15, 2024
Also in Grand Falls