Replacement of the Wellington & District Community Centre

Picton, Ontario

completeRecreationCC
Federal contribution
$3.9M
$3,927,503
Federal share33%

of $11.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Prince Edward
Construction start
Aug 17, 2009(actual)
Construction end
Dec 12, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Sep 21, 2009
  • Construction end4 weeks lateforecast Nov 15, 2010