Replacement of Watermains and Sanitary Sewers
Federal contribution
$1.3M
$1,259,306
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Prince Edward
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Jul 23, 2010(actual)
Against the original forecast
- Construction end5 months earlyforecast Dec 7, 2010