Sandbanks Road Repairs

Picton, Ontario

completeHighways and RoadsISF
Federal contribution
$350,000
Federal share50%

of $700.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Oct 8, 2010(actual)
Construction end
Nov 29, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 7, 2010
  • Construction end4 months earlyforecast Mar 31, 2011

Also in Picton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39692 in the federal list. How to read these figures.