Improvements to the Deseronto Wastewater Treatment System
Federal contribution
$1.5M
$1,500,000
Federal share33%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Deseronto
- Construction start
- Oct 6, 2014(actual)
- Construction end
- Mar 31, 2016(actual)
Against the original forecast
- Construction start3.5 years lateforecast Mar 31, 2011
Also in Deseronto
- Upgrade and renewal of the Deseronto Water Treatment Plant$2.4M
- Renovation of Deseronto Community Centre$675.0K
- Rehabilitation and renovation of a Community Centre$269.2K
- Deseronto Town Hall - Covid-19 Updates$80.0K
- Sewage Pumping Stations Electrical Upgrades and Manual Transfer Switch Installations$66.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23133 in the federal list. How to read these figures.