Deseronto Town Hall - Covid-19 Updates
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Deseronto
- Construction start
- Mar 17, 2022(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start8 months lateforecast Jul 5, 2021
- Construction end16 months lateforecast Sep 3, 2021
Also in Deseronto
- Upgrade and renewal of the Deseronto Water Treatment Plant$2.4M
- Improvements to the Deseronto Wastewater Treatment System$1.5M
- Renovation of Deseronto Community Centre$675.0K
- Rehabilitation and renovation of a Community Centre$269.2K
- Sewage Pumping Stations Electrical Upgrades and Manual Transfer Switch Installations$66.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60955 in the federal list. How to read these figures.