Renovation of Deseronto Community Centre

Deseronto, Ontario

completeRecreationCC Top Up
Federal contribution
$675,000
Federal share45%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Deseronto
Construction start
May 31, 2010(actual)
Construction end
Mar 15, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 17, 2010

Also in Deseronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28035 in the federal list. How to read these figures.