Construction of an Outdoor Artificial Turf Field
Federal contribution
$425,009
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Beckwith
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end17 months lateforecast May 31, 2010
Also in Carleton Place
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23135 in the federal list. How to read these figures.