Back to projects

Construction of the Minden Elevated Storage Tank

Minden Hills, Ontario

completeDrinking WaterCC
Federal contribution
$802,083
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Minden Hills
Construction start
Jan 4, 2010(actual)
Construction end
Jun 28, 2011(actual)