Replacement of the Sedgewick Bridge
Federal contribution
$571,078
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 19, 2020
20212022
Built
Approved 7 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Minden Hills
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Nov 17, 2022(actual)
Also in Minden Hills