Expansion to the Township of Algonquin Highlands Airport
Federal contribution
$1.3M
$1,263,167
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Algonquin Highlands
- Construction start
- Oct 4, 2010(actual)
- Construction end
- Jun 30, 2015(actual)
Against the original forecast
- Construction start7 months earlyforecast May 1, 2011
- Construction end6 months lateforecast Dec 30, 2014
Also in Minden Hills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23926 in the federal list. How to read these figures.