Sewage Pump Station Upgrades - Northern

Prince Albert, Saskatchewan

completeWastewaterCC
Federal contribution
$423,332
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 4, 2011(actual)
Construction end
May 9, 2012(actual)

Against the original forecast

  • Construction start2.2 years lateforecast May 1, 2009
  • Construction end7 weeks earlyforecast Jun 30, 2012

Also in Prince Albert