Sewage Pump Station Upgrades - Northern
Federal contribution
$423,332
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
2009201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Northern Village of LA LOCHE
- Construction start
- Jul 4, 2011(actual)
- Construction end
- May 9, 2012(actual)
Against the original forecast
- Construction start2.2 years lateforecast May 1, 2009
- Construction end7 weeks earlyforecast Jun 30, 2012