Schedule

Announced and approvedFeb 20, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Construction start
Apr 10, 2011(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start23 months lateforecast May 1, 2009
  • Construction end3 months earlyforecast Jun 30, 2012