Back to projects

Water & Sewer Main Replacement - Northern

Prince Albert, Saskatchewan

completeDrinking WaterCC
Federal contribution
$378,000
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Creighton
Construction start
Jul 6, 2009(actual)
Construction end
Nov 30, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2009
  • Construction end2.3 years earlyforecast Mar 12, 2012

Also in Prince Albert