Installation of Water Meters
Federal contribution
$82,534
Federal share33%
of $247.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Red Rock
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Feb 28, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2009
Also in Red Rock
- Red Rock Water Pollution Control Plant$7.6M
- Replacement and Rehabilitation of Newton Avenue, Brompton Road and Stadler Avenue Water and Wastewater Infrastructure$1.1M
- Red Rock Recreation Centre Rehabilitation$720.1K
- Improvements to Red Rock Recreation Centre$271.8K
- Recreation Center Arena Roof Retrofit and Repair$80.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23189 in the federal list. How to read these figures.